Reliability assessment of an isolated hybrid microgrid using Markov modeling and Monte Carlo simulation

The importance of conducting adequacy assessments of standalone systems with integrated renewable generation sources is growing. In this work, the focus is placed on the reliability assessment of an isolated microgrid operating on renewable energy generated by wind turbines (WTs) and photovoltaic (P...

Full description

Permalink: http://skupni.nsk.hr/Record/nsk.NSK01001145120/Details
Matična publikacija: Engineering review (Online)
41 (2021), 2 ; str. 62-73
Glavni autori: Saleem, Ahmad F. (Author), AlMuhaini, Mohammad
Vrsta građe: e-članak
Jezik: eng
Predmet:
Online pristup: https://doi.org/10.30765/er.1478
Hrčak
LEADER 02470naa a22003374i 4500
001 NSK01001145120
003 HR-ZaNSK
005 20230127104647.0
006 m d
007 cr||||||||||||
008 220803s2021 ci a |o |0|| ||eng
024 7 |2 doi  |a 10.30765/er.1478 
035 |a (HR-ZaNSK)001145120 
040 |a HR-ZaNSK  |b hrv  |c HR-ZaNSK  |e ppiak 
042 |a croatica 
044 |a ci  |c hr 
080 1 |a 621.3  |2 2011 
100 1 |a Saleem, Ahmad F.  |4 aut  |9 HR-ZaNSK 
245 1 0 |a Reliability assessment of an isolated hybrid microgrid using Markov modeling and Monte Carlo simulation  |h [Elektronička građa] /  |c Ahmad F. Saleem, Mohammad AlMuhaini. 
300 |b Ilustr. 
504 |a Bibliografija: 9 jed. 
504 |a Abstract. 
520 |a The importance of conducting adequacy assessments of standalone systems with integrated renewable generation sources is growing. In this work, the focus is placed on the reliability assessment of an isolated microgrid operating on renewable energy generated by wind turbines (WTs) and photovoltaic (PV) panels. Batteries for storage were included in the model because of their crucial role in the system"s feasibility. Additional micro-gas turbines (MGTs) served as conventional backup. The sequential Monte Carlo simulation (SMCS) method was used to carry out simulations of the system, which was modeled using Markov matrices. Input data, such as wind speed, solar irradiance, and ambient air temperature, were used to simulate the power outputs of the generators. These historical data were fitted into appropriate distributions to extract corresponding parameters when simulating essential key factors necessary to produce the renewable power generation models. The adequacy model of the MGTs was obtained by employing the two-state reliability model, which was also superimposed with the generation models of WTs, PV panels, and batteries. The IEEE Roy Billinton test system (RBTS) was used for demand modelling. Common reliability indices were computed, and the system availability margins were evaluated. 
653 0 |a Fotonapon  |a Vjetroturbine  |a Plinska turbina  |a Generatori 
700 1 |a AlMuhaini, Mohammad  |4 aut  |9 HR-ZaNSK 
773 0 |t Engineering review (Online)  |x 1849-0433  |g 41 (2021), 2 ; str. 62-73  |w nsk.(HR-ZaNSK)000848891 
981 |b Be2021  |b B03/21 
998 |b tino2301 
856 4 0 |u https://doi.org/10.30765/er.1478 
856 4 0 |u https://hrcak.srce.hr/247935  |y Hrčak 
856 4 1 |y Digitalna.nsk.hr