Implementacija turbinske regulacije na NI cRIO platformi

Sažetak na hrvatskom: Svrha ovog diplomskog rada je napraviti sustav turbinske regulacije za hidroelektranu Golubić koja se nalazi na rijeci Butišnici, pritoci rijeke Krke. Simulacijski model je napravljen u programskom okruženju Labview te je prebačen na National Instruments cRIO platformu koja pro...

Full description

Permalink: http://skupni.nsk.hr/Record/fer.KOHA-OAI-FER:49482/Details
Glavni autor: Mohor, Tin (-)
Ostali autori: Mišković, Nikola (Thesis advisor)
Vrsta građe: Drugo
Impresum: Zagreb, T. Mohor, 2016.
Predmet:
LEADER 02540na a2200229 4500
003 HR-ZaFER
008 160221s2016 ci ||||| m||| 00| 0 hr d
035 |a (HR-ZaFER)ferid4350 
040 |a HR-ZaFER  |b hrv  |c HR-ZaFER  |e ppiak 
100 1 |a Mohor, Tin 
245 1 0 |a Implementacija turbinske regulacije na NI cRIO platformi :  |b diplomski rad /  |c Tin Mohor ; [mentor Nikola Mišković]. 
246 1 |a Implementation of tubine control on a NI cRIO platform  |i Naslov na engleskom:  
260 |a Zagreb,  |b T. Mohor,  |c 2016. 
300 |a 45 str. ;  |c 30 cm +  |e CD-ROM 
502 |b diplomski studij  |c Fakultet elektrotehnike i računarstva u Zagrebu  |g smjer: Automatika, šifra smjera: 46, datum predaje: 2016-07-01, datum završetka: 2016-07-12 
520 3 |a Sažetak na hrvatskom: Svrha ovog diplomskog rada je napraviti sustav turbinske regulacije za hidroelektranu Golubić koja se nalazi na rijeci Butišnici, pritoci rijeke Krke. Simulacijski model je napravljen u programskom okruženju Labview te je prebačen na National Instruments cRIO platformu koja provodi zadane algoritme i izmjenjuje podatke s okolinom u stvarnom vremenu. Regulator je napravljen na PLC-u te se sastoji od tri regulatora, PI regulatora otvora privodnog kola te PID regulatora brzine vrtnje spojenog u paralelu s PI regulatorom snage. Testiranja su provedena u hardware-in-the-loop načinu testiranja te je napravljeni regulator spreman za uporabu u hidroelektrani uz potrebu finog podešavanja na samoj hidroelektrani. 
520 3 |a Sažetak na engleskom: The purpose of this master thesis is to make a turbine control system for hydroelectric power plant Golubić, which is located on the river Butišnica, a tributary of the river Krka. The simulation model was made in the programming environment Labview and was afterwards transferred to the National Instruments cRIO platform that implements the default algorithms and exchanges data with the environment in real time. The controller is designed on PLC and consists of three controllers, PI wicket gate controller and PID speed controller that are connected in parallel with the PI controller. The tests are performed in hardware-in-the-loop testing mode and the designed controller just needs to be fine-tuned and is then ready to use on the hydroelectric power plant. 
653 1 |a hidroelektrana  |a HIL simulacija  |a turbinska regulacija  |a cRIO platforma  |a Labview 
653 1 |a hydropower plant  |a HIL simulation  |a turbine regulation  |a cRIO platform  |a Labview 
700 1 |a Mišković, Nikola  |4 ths 
942 |c Y 
999 |c 49482  |d 49482